Recent content by Bluejay

  1. B

    Odenak | 665 Albert St. | 105+120m | 31+36s | Dream+Multifaith | Perkins&Will+KPMB+Two Row | U/C

    It is moving fast but it has been 1 floor per week for this build. It's been 17 weeks since the first level of the 'tower portion'
  2. B

    General Update/Rumour Thread

    Unfortunately I do not have any updates on that project. I own a consulting company who works with multiple developers (high-rise projects) offering project management services from pre-construction to completion. We do not use or post our tenders on any sites as we invite our preferred...
  3. B

    General Update/Rumour Thread

    Wrong again. I should be able to share it by Friday.
  4. B

    General Update/Rumour Thread

    That’s not correct at all. I cannot name the architect at this point but you guys can put the math together and figure it out. If you don’t, it will be public shortly.
  5. B

    General Update/Rumour Thread

    Here is a sneak peak of the 275 Rideau project (LCBO King Edward & Rideau) It is a major improvement from the first design. This is being proposed at 28 floors at 85m in height, L-Shaped tower with commercial space fronting Rideau St.
  6. B

    Renaissance Marriot / OROS Apartments | 395 Slater St. | 118m | 36s | Rimap | IBI+GeigerHuot | U/C

    I can dig some up. Once I do, I will share. Designer for the hotel portion interior is Design Agency.
  7. B

    Renaissance Marriot / OROS Apartments | 395 Slater St. | 118m | 36s | Rimap | IBI+GeigerHuot | U/C

    No, there are no open areas in this one. They wanted to maximize the second level board/meeting rooms for this location. This Renaissance will actually be the first in their new design for this brand. High end finishes, lots of millwork and fancy ceilings in the lobby and restaurant areas...
  8. B

    Renaissance Marriot / OROS Apartments | 395 Slater St. | 118m | 36s | Rimap | IBI+GeigerHuot | U/C

    No retail in this building. Hotel has a full service restaurant & bar.
  9. B

    Odenak | 665 Albert St. | 105+120m | 31+36s | Dream+Multifaith | Perkins&Will+KPMB+Two Row | U/C

    Yes, top out is projected by October 2026. This project is a logistical nightmare with Slater St being the only staging and work area that also has lane use time restrictions. Once they hit typical floors with the fly forms, you are looking at an average of 7-8 days per floor plus more for the...
  10. B

    Relevé | 78+95.5m | 23+29s | Main+Main+Westdale+Centurion | Arcadis IBI

    Yes, that is the plan. It's all owned by the same person. Preliminary massing plans are hopefully going to be completed by the end of the year. This is very early on so don't get too excited yet.
  11. B

    Odenak | 665 Albert St. | 105+120m | 31+36s | Dream+Multifaith | Perkins&Will+KPMB+Two Row | U/C

    The 36 floor tower is slated to top out by March the latest...depending on winter conditions though.
  12. B

    Relevé | 78+95.5m | 23+29s | Main+Main+Westdale+Centurion | Arcadis IBI

    Not much anyone could do since Mr. Flemming refused multiple offers to sell that property. It may happen eventually, but not anytime soon. Good news is that there are very preliminary discussions on a potential developer team getting together to put together a proposal for "L" shaped lot 368...
  13. B

    Relevé | 78+95.5m | 23+29s | Main+Main+Westdale+Centurion | Arcadis IBI

    Move-ins for tower A have been ongoing for a while. Tower B will start move-ins within the next few weeks.
  14. B

    Renaissance Marriot / OROS Apartments | 395 Slater St. | 118m | 36s | Rimap | IBI+GeigerHuot | U/C

    Second floor forming has started. This one will take approximately two and a half weeks to complete and then the tower will start rising rapidly.
  15. B

    Moxy Marriott / Major Apartments | 126 York St. & 151 George St. | 72m | 22s | Rimap | Le Groupe Architex

    Since the balcony glass topic is the 'current thing' on these forums, I am happy to share that the balcony glass at Renaissance will be bypassing the balcony slab edge with a shaded frit section of glass. It will be a step up from the Releve's tin covering the balcony slab edges. Maybe it will...