O-Train East-West Line 1 & Line 3

Concrete curbing and initial asphalt paving is complete for the new westbound western parkway alignment. Piles of fresh top soil were being dumped on the new asphalt for the adjacent landscaping and various potted plants were seen by the Cleary under pass for future planting.
20251029_111455.jpg
20251029_111439.jpg
m
 
Trial Running on the East line may start in Q2 2026 per Transit committee.

The issues before substantial completion are: retrofitting station support systems, resolving platform edge camera functions, and adjusting rail infrastructure at specific segments.
 
Trial Running on the East line may start in Q2 2026 per Transit committee.

The issues before substantial completion are: retrofitting station support systems, resolving platform edge camera functions, and adjusting rail infrastructure at specific segments.
Nice to finally have a list. Was that so hard?

Also, train availability.
 
per docs for next week's transit committee, the most recent estimated date for substantial completion of the East was March 4th (today).

Some info on the West Extension. The Overhead Catenary System is installed from Moodie to Lincoln Fields and to Algonquin,