M Marcus CLS Active Member Member Bio Joined Jan 8, 2024 Messages 127 Reaction score 211 Jan 21, 2025 #16 Tower crane going up today.
M Marcus CLS Active Member Member Bio Joined Jan 8, 2024 Messages 127 Reaction score 211 Mar 11, 2025 #17 Concrete forming at bottom level.
M Marcus CLS Active Member Member Bio Joined Jan 8, 2024 Messages 127 Reaction score 211 Mar 28, 2025 #18 Beginning of 1st floor slab has been poured.
M Marcus CLS Active Member Member Bio Joined Jan 8, 2024 Messages 127 Reaction score 211 May 9, 2025 #19 Forming has reached ground level.
hoggytime Senior Member Staff member Member Bio Joined Dec 7, 2023 Messages 1,656 Reaction score 1,414 Location Aylmer May 9, 2025 #20 That was fast!!
M Marcus CLS Active Member Member Bio Joined Jan 8, 2024 Messages 127 Reaction score 211 Jun 17, 2025 #21 Progress now at 3rd floor completed.
B btap Active Member Member Bio Joined Dec 18, 2023 Messages 154 Reaction score 168 Jul 8, 2025 #22 This one is topped out .
M Marcus CLS Active Member Member Bio Joined Jan 8, 2024 Messages 127 Reaction score 211 Wednesday at 8:45 PM #24 Exterior cladding preparation in progress. Vapour barrier instalation seems to be complete followed by fiberglass insulation. Insulating foam panel decking be hoisted for the roof and various patio terraces.
Exterior cladding preparation in progress. Vapour barrier instalation seems to be complete followed by fiberglass insulation. Insulating foam panel decking be hoisted for the roof and various patio terraces.