Any schedule you know of for Renaissance?
Yes, top out is projected by October 2026. This project is a logistical nightmare with Slater St being the only staging and work area that also has lane use time restrictions. Once they hit typical floors with the fly forms, you are looking at an average of 7-8 days per floor plus more for the 16th & 17th level pool/amenity floor.
 